3 Commissioning the switchgear
Installing and starting up the switchgear is an important event for the System Administrator. The
following steps must be followed when commissioning the switchgear.
Step 1: Reset Passwords.
See Passwords
on page 13.
Step 2: Set User Settings.
See DEH-231 Entellisys Low Voltage Switchgear System User Manual.
Step 3: Set Local HMI flags.
See Local HMI
on page 17.
Step 4: Set System Time Synchronization.
See Time synchronization
on page 19.
Step 5: Configure System for Remote Communications.
See Configuring the switchgear for remote communications
on page 21.