General rack placement rules and other information:
• Locate heaviest components at the bottom of the rack (i.e., UPS, then servers or storage, etc.).
• Do not extend more than one component on side rails at a time.
• Maximum of three UPSs (including no more than two APC 5000 UPSs) per rack.
• Utilize sidewall compartments for mounting PDUs and console switches prior to using EIA space.
• When mounting components in a rack, consider user and service requirements.
• When selecting length of power, console and storage cables, consider extension of cable management
arms and overall cable routing.
• BTUs = Watts x 3.41.
Notes:
1. Optional rack power cords: P/N 94G6667 - 14ft NEMA 5-15P; P/N 94G7448 - 14ft IEC 320-C14.
2. Additional power cords are not required. This power supply option shares use of line cords provided
with the base system. Should be ordered in pairs to maintain redundancy.
3. Refer to Appendix BladeCenter Power Upgrade Guidelines for important information that will help
determine when a BladeCenter power module upgrade is necessary.
Power Supply Options
Standard Power Cords
1
Power Supply Part Number Usable with
IEC 320-C13 IEC 320-C19
6ft NEMA 5-15P
6952301
9ft NEMA 5-15P
6952300
9ft IEC 320-C14
36L8886
Y-cable 2xC13/C14 25R2567
9ft IEC 320-C20
74P4430
14ft IEC 320-C14
12J5995
8.2ft IEC 320-C20
00N7701
8.2ft NEMA 5-15P
12J5112
370w 31P6133 x255
2
585w 90P5280 x336 1
625w 26K5097 x346
670w 26K9560 x236
1300w 13M7413 x366 1
2000w 26K4816 BladeCenter
3
2
DS300 Upgrade 13N1775 1701-1RL 1