Mode – Displays the current STP mode. The STP mode is selected in the STP
Configuration screen. The possible field values are:
STP – Classic STP is enabled on the device.
RSTP – Rapid STP is enabled on the device.
Fast Link Operational Status – Displays the Fast Link status for the interface. If Fast
Link is enabled for a port, the port is automatically placed in the forwarding state. The
possible field values are:
Enabled – Fast Link is enabled on the interface.
Disabled – Fast Link is disabled on the interface.
Status – Displays the RSTP status for the interface. The possible field values are:
Enabled – RSTP is enabled on the interface.
Disable – RSTP is disabled on the interface. This is the default value.
Point-to-Point Admin Status – Select whether a point-to-point link is established, or if
the device is permitted to establish a point-to-point link. The possible field values are:
Enable – Enable a point-to-point link, or configure to automatically establish a point-
to-point link. To establish communications over a point-to-point link, the originating
PPP first sends Link Control Protocol (LCP) packets to configure and test the data
link. After a link is established and optional facilities are negotiated as needed by the
LCP, the originating PPP sends Network Control Protocol (NCP) packets to select and
configure one or more network layer protocols. When each of the chosen network
layer protocols has been configured, packets from each network layer protocol can be
sent over the link. The link remains configured for communications until explicit LCP
or NCP packets close the link, or until some external event occurs. This is the actual
switch port link type. It may differ from the administrative state.
Disable – Disable point-to-point link.
–Auto – Enable the device to automatically establish a point-to-point link.
Point-to-Point Operational Status – Displays the point-to-point operating state.
Activate Protocol Migration – Activate sending Link Control Protocol (LCP) packets to
configure and test that the data link is enabled.
2. Select the interface.
3. Select the Point-to-Point Admin Status from the list in the provided field in the first row.