APC 3500 Power Supply User Manual


 
Smart-UPS® VT and MGE™ Galaxy™ 3500 10-30 kVA 208 V MBP Installation 12
UPS connections.
Note: UPS cables can enter through the top or the bottom of the MBP. However, BOTTOM is
recommended.
Refer to the Smart-UPS VT 10-30kVA or MGE Galaxy 3500, 208V Installation Manual for
MBP cable connections at the UPS.
1. Connect the four UPS inputs [L1, L2, L3, N, top-to-bottom] to the Q1 Switch in the MBP. Use a
4mm Allen wrench and torque to 60in-lbs [7Nm].
2. Connect the four UPS outputs [L1, L2, L3, N, top-to-bottom] to the Q2 Switch in the MBP. Use a
4mm Allen wrench and torque to 60in-lbs [7Nm].
3. Connect the two UPS control wires to Pins 7 and 8 in the MBP Control Terminal Block. Use a
standard (flathead) screwdriver and make the screws hand-tight.
UPS Inputs to Q1
UPS Outputs to
Control Wires [7, 8]
Switch [L1, L2, L3, N]
Q2 Switch [L1, L2, L3, N]