Appendix A Site Preparation and Maintenance Records
Site Preparation Checklist
Power evaluation:
Input power type
Power receptacles
Receptacle proximity to the equipment
Dedicated (separate) circuits for power
redundancy
UPS for power failures
Grounding: proper gauge wire and lugs
Circuit breaker size
Grounding evaluation:
Data center ground
Cable and interface equipment evaluation:
Cable type
Connector type
Cable distance limitations
Interface equipment (transceivers)
EMI evaluation:
Distance limitations for signaling
Site wiring
RFI levels
Table A-1 Site Planning Checklist (continued)
Planning Activity Verification Time and Date