Emerson 7ACTB Switch User Manual


 
INSTALLATION
(continued )
1 --- 3
RED
RED
GREEN
GREEN
observe
these lights
RED RED RED
Figure 1-3. Standard controls and indicators.
Functional Test
Read all i nstructions on the Wiring Diagrams and labels
affixed to the ACTB. Note t he control features that a re
provided and review their operation before proceeding.
After installing the ACTB check the following:
– Bypass Handle should be in the OPEN position.
– Isolation Handle should be in the CLOSED position.
CN transfer switch should be CLOSED.
CE transfer switch should be OPEN.
If handles are not in correct positions, follow instructions
for Bypassing and Isolating the automatic transfer switch
in Section 3. Do not force the handles. Electrical
interlocks prevent a wrong sequence of operation.
1–VoltageChecks
First check nameplate on transfer switch; rated voltage
mustbethesameasnormalandemergencylinevoltages.
Useextremecautionwhenusingameter
to measure voltages. Do not touch power
terminals; shock, burns, or death could resul t !
Perform steps 1–6 at the right. Observe the status lights.
See Figure 1–3.
Black square means light is on.
White square means light is off.
* If necessary, adjust voltage regulator on generator per the
manufacturer’s recommendations. The ACTB will respond only
to rated voltage specified on the nameplate.
Now continue to 2 Electrical Operation on next page.
1
Close the normal source circuit
breaker. The Transfer Switch
Connected To Normal and the
Normal Source Accepted lights
should come on.
2
Use an accurate voltmeter to
check phase to phase and
phase to neutral voltages pres-
entatthetransferswitchnormal
source terminals.
3
Close the emergency source
circuit breaker. Turn the Engine
Control switch to Run to start
the generator. The Transfer
Switch Connected To Normal &
Emergency Source Accepted
lights should come on.
4
Use an accurate voltmeter to
check phase to phase and
phase to neutral voltages pres-
ent a t the transfer switch emer-
gency source terminals.*
5
Useaphaserotationmeterto
check phase rotation of emer-
gency source; it must be the
same
as the normal source.
A
B
C
6
Turn Engine Control switch to
Auto to stop the generator. The
Emergency Source Accepted
light should go off. Then put the
starting control selector switch
(on generator set) in automatic
position. Close enclosure door.