3. Testing
Test Incoming Service Lines:
To test the incoming service lines, disconnect the jumper cord from the “TEST” jack,
which will deactivate the “OUT” jack and all distribution ports. Plug the tester into “TEST”
jack to verify phone service. Reconnect the jumper cord between the “TEST” jack and
“OUT” jack to restore service to the distribution ports.
Test Distribution Cabling:
To test the distribution cabling, disconnect the jumper cord from the “OUT” jack, which will
deactivate service on all distribution ports. Plug the tester into the “OUT” jack to verify
cabling. Reconnect the jumper cord between the “TEST” jack and “OUT” jack to restore
service to the distribution ports.
Note: Use a qualification tester for testing this bridged voice distribution module.