Step 2:
Cut a rough opening through the wall at the correct height, so when finished with the standard 2" x 4" wood framing,
the opening corresponds to the following dimensions:
• BVHD3100 (100"), the rough wall opening must measure at least: 91-11/16" W x 54-13/16" H.
100" BigVizion Wall Opening Diagram. (Figure 1-1)
• BVHD3090 (90"), the rough wall opening must measure at least: 83" W x 50" H.
90" BigVizion Wall Opening Diagram. (Figure 1-2)
• BVHD3080 (80"), the rough wall opening must measure at least: 74-1/4" W x 45" H.
80" BigVizion Wall Opening Diagram. (Figure 1-3)
NOTE: The above listed dimensions are suggested minimums, and can be made slightly larger to accommodate
shim material. Wall must be level on all sides. Check with plumb lines and level.
IMPORTANT!
See the next three diagrams of the 100"/90"/80" for detailed dimensions of required wall opening.