5. Connection Procedure
5.1 For M32100T-SDI-E or M32170T-SDI.
(1) Mount the NQPACK144SD on the user system
(2) Connect the YQPACK144SD on the NQPACK144SD.
(3) Secure the four corners of the YQPACK144SD with the
YQ-GUIDE’s.
(4) Mount the M32186T2-PTC on the YQPACK144SD.
(5) Set the clock select switch.
(6) Mount the M3T-PTC-CNV on the M32186T2-PTC.
(7) Connect the emulation pod probe to the M32186T2-PTC
via the SDI MCU control interface cable and the SDI trace
interface cable.
(7)
M32186T2- PTC
YQPACK144SD
YQ-GUIDE(x4)
NQPACK144SD
144-pin 0.5mm pitch
(144P6Q-A) foot pattern
(1)
(2)
(3)
(4)
Clock select switch
(5)
(6)
●
: No.1 pin
Be sure to match the position of No. 1 pin of the foot pattern and each part.
M3T- PTC-CNV
(separately available)
Connection to the M32100T-SDI-E or M32170T-SDI
Interface cables of the pod probe