Planning a UPS system should include the following considerations:
The total demand of the protected system shall dictate the output power rating (VA).
Allow a margin for future expansion or calculation inaccuracies from measuring
power requirements.
Backup time needed will determine the battery size needed. If the load is less than
the UPS nominal power rating then the actual backup time will be longer.
The following options are available:
External Battery Cabinets, and
Connectivity options (Remote Contact, SNMP/WEB card).
The following UPS models are available.
Model
Backup time Internal
batteries
Recharge time to 90%
capacity
UPS 1000VA 7 min 4 hours
UPS 1500VA 6 min 4 hours
UPS 2000VA 7 min 4 hours
UPS 3000VA 6 min 4 hours
Additional External Battery Cabinets are available if more back-up time is needed.