1.7 Operation Test
1. Connect the UPS to the wall receptacle.
2. Push on the Main Switch to check the Green Line ( ) LED is on.
3. Connect your computer equipment with sockets of the UPS and pull off
the input power cable of the UPS from the wall receptacle to check if the
Line ( ) LED is flashing every 3 seconds. Meanwhile, please check if
alarm buzzer is beeping.
4. Try the field working condition by running some application programs on
your computer and repeating step.
5. Check if the UPS is initiated properly to support continuous operation.
IMPORTANT NOTICE: Plug the UPS into the wall outlet to charge the UPS for
over 10 hours before using the UPS.
1.8 Front Panel Explanations
On the front panel You can found 2 LED for an easy diagnostic.
LED
Information
Main Switch
To Control on/off the UPS when Utility is normal.
To enable “DC-Start” Function when Utility fails. (To enable
DC Start properly, you are recommended to connect <80%
output load with the UPS only). P.S. Make sure the
computer connected to the UPS is switched on before
enable the "DC-Start" function. You are not recommended
to add some other computer or peripherals after DC-Start
function is activated.
LED Line ( )
Green LED remains standstill when Utility is normal.
Green LED flashes every 3 seconds and simultaneously
buzzer alarms continuously when Utility failure.
Green LED flashes every 3 seconds when the UPS is in
Battery charging mode.
Led Line flashes every 0.5 seconds and buzzer alarms