16 HP StorageWorks Disk Array XP128: Site Preparation Guide
Site planning timetable
The following guidelines can be used to monitor the progress of your
pre-installation preparation. The time between placing an order and actual
arrival can vary, and we recommend conferring with your HP
representative to determine the best estimated delivery dates for preparation
of your site.
The following are items that may require several weeks of lead time to
complete:
Acquiring required power connectors
Arranging for an electrician
Adding or modifying air conditioning
Building alterations
Placing an order for data comm equipment
Due to potential delays, we recommend that the suppliers of the listed
services be contacted as soon as you have placed your order:
Schedule the site planning visit with your HP CE to discuss questions
concerning site planning.
Select an appropriate location for the disk array and create a plan
outlining the physical arrangement of the equipment, including related
furniture.