Panduit PN380C Power Supply User Manual


 
DPOE™ Power System User Manual Part Number: PN380C
POWER PLANT MOUNTING AND WIRING
WARNING:
Ensure all AC and DC power sources are off and disconnected.
8
Mechanical Mounting
The DPOE™ Power System chassis is installed in a standard EIA 19” rack. It is recommended that one
person lift the chassis into the proper rack place while another person installs the supplied mounting
screws. Tighten the screws with a torque wrench to the setting according to Table 6: Recommended
Torque Settings.
Mounting Brackets
Figure 5: Chassis (Front View)
Slots for Rectifiers
In shelf
distribution
Support Shelf Mounting (Optional)
After securing the DPOE™ Power System chassis with mounting screws in the front, an optional rack
mount shelf may be installed underneath the chassis on the backside of the rack to alleviate potential
sagging of the chassis unit, due to weight distribution when mounted on a 2-post rack. PANDUIT offers a
1RU shelf (part # SRM19FM1) with a load rating of 30 lbs that will help support the chassis. For optimum
saftety, a 2 RU shelf (PANDUIT part # SRM19FM2 – shown below) with a load rating of up to 50 lbs may
be installed.
Attach power chassis to front of rack
using Mounting Brackets
Optional Rack Mount Shelf
(attached to back of rack with
shelf turned upside down)
Figure 6: Optional Rack Mount Shelf
NOTE:
Optional rack shelf is actually installed upside down to the rear of the rack to allow
power chassis to rest on the flat side of the shelf.