Cable Installation
152602 2–9
To make PV Array #2 and GT100E #2 connections:
1. Route the GT100E #2 cables through the access panel and connect the
cables to GT100E UNIT #2 PV(+) and PV(-) terminals, see Figure 2-
6.
2. Route the PV Array #2 cables through the access panel and connect
the cables to PV ARRAY #2 PV(+) and PV(-) terminals, see Figure 2-
6.
3. Route the PV Array #2 ground cable through the access panel and
connect the cable to PV ARRAY #2 GND terminal see Figure 2-6.
Figure 2-6
PV Array #2 and GT100E #2 Connections
Combiner Box
PV ARRAY #2
PV (+) Terminal
Combiner Box
PV ARRAY #2
PV (-) Terminal
Combiner Box
GT100E #2
PV (+) Terminal
Combiner Box
GT100E #2
PV (-) Terminal
Combiner Box
PV ARRAY #2
GND Terminal