Power Up and Verification
This section tells how to power up the concentrator and verify that it is
working correctly.
Switch the power supply On/Off switch to the On (|) position.
The Power Supply LED(s) on the ONline Controller Module light when the
unit is powered up correctly. The verification procedure is split into the
following areas:
fan operation
power supply operation
network operation