Allied Telesis AT-SBX31XZ4 Switch User Manual


 
SwitchBlade x3112 Installation Guide
79
Preparing the Equipment Rack
This section explains how to prepare the equipment rack for the
installation of the chassis. The procedure requires the following items:
#2 Phillips-head screwdriver (not provided)
Two equipment rack screws (not provided)
To prepare the equipment rack for the installation of the AT-SBx3112
Chassis, perform the following procedure:
Caution
The chassis is heavy and should be mounted as low as possible in
the equipment rack to maximize vertical stability.
1. Reserve 311.1 mm (12.25“) of vertical rack space for the installation of
the AT-SBx3112 Chassis, as shown in Figure 34 on page 80.
2. Do not mount any other equipment within 152.4 mm (6”) above this
space during installation. This additional vertical space is temporary
and allows you enough room to lift and tilt the chassis into its position
in the equipment rack without hitting other equipment, as shown in
Figure 40 on page 87. You may use this additional space for other
network equipment after the chassis is installed.