American Power Conversion SURT006 Power Supply User Manual


 
CHAPTER 3: INSTALLATION
8
Unpacking
Inspection
Contents
Installing the Step-Down Transformer
Installing in a Four-Post Rack
Figure 8: AP9621 / SURT005 / SURT006
Figure 9: SUTF3 / SYTF2 / SYTF2J /
SYTF3 / SYTF3J
1. Install the mounting rails using the instructions contained
in the Rail Kit.
2. Slide the Step-Down Transformer frame into the rack.
The Step-Down Transformer is heavy.
Three people must support the unit.
3. To secure the Step-Down Transformer frame in the rack,
screw the four decorative screws through the holes in the
ears of the UPS and into the screw clips.
4. If the bezel has not already been attached, align the tabs
on the sides of the bezel with the slots on the front of the
Step-Down Transformer and gently snap it into place.
Install the bezel with the rear fins
facing down.
The Step-Down Transformer is packaged in a robust shipping carton. Carefully remove the package contents. The
packaging is recyclable; save it for reuse or dispose of it properly.
Inspect the equipment upon receipt. APC has designed robust packaging for your product. However, accidents
and damage may occur during shipment. Notify the carrier and dealer if there is damage or missing equipment.
Check the packaging contents. The shipping package contains the Step-Down Transformer, mounting rails, and
mounting hardware. Your package may contain a Bezel Kit. If the bezel is not already installed, snap it on to the
UPS as instructed below.
This section provides information on the steps required to install and connect the Step-Down Transformer.
Follow the instructions contained in the Addendum SU Rack-Mount Rails 2U-5U sheet (990-7034G) to mount
the rails in your NetShelter or 19 in (46.5 cm) rack.
*It is recommended that the Step-Down Transformer is installed directly above the UPS in the rack.