American Power Conversion XR Power Supply User Manual


 
Operation – Restart Procedure
24 Smart-UPS® VT 10-30 kVA, 208/220 V and XR Battery Enclosure Operation Manual 990-1599B
After system boot-up, the display will automatically prompt you on how to confirm/select voltage
and frequency as shown in the following.
Voltage confirmation
At the restart, the display will prompt you through the following screens:
When the Confirm Voltage prompt appears on the screen, select desired voltage and press
ENTER.
When the prompt Apply load appears, select Yes if you want the UPS to provide a load output
now. (If you do not want a UPS load output at this point, select No).
LOAD ON LED is now lit, and the display will show the Confirm Menu Screen.
Note
Wait approximately 30 seconds for the system to boot up and carry out self test.
See display introduction under The Display.
Note
The UPS is now ready to support the load.
Note
Auto-detection on frequency – if problem occurs call APC Customer Support.
Confirm Voltage
Use 208V
Yes, use 208V
No, select another
Apply load?
Yes
No
Chrg xxx% ||||||||||
Load xxx% ||||||||||
xxx Vin xxxVout xxHz
Runtime: xxhr xxmin
Status screen