APC AP9631 Network Card User Manual


 
UPS Network Management Card 2 User’s Guide34
Reboot UPS (Web
interface)
ups -c Reboot
(command line
interface)
Restarts the attached equipment by doing the following:
• Turns off power at the UPS after Shutdown Delay.
• Turns on power at the UPS after the UPS battery capacity returns to at least the
percentage configured for Minimum Battery Capacity or can support the load for
the time configured for Return Runtime Duration. (The parameter differs by UPS
model.) The UPS then waits the time specified as Return Delay. See “The
shutdown option” on page 36.
• For a UPS with outlet groups, Power On Delay occurs after the UPS turns on and
before an outlet group turns on. On the UPS tab, configure Power On Delay for
each outlet group by using the settings option under Outlet Groups. See “The
settings option (including automatic load-shedding)” on page 40.
For a Synchronized Control Group action:
1. This option turns off power at the UPSs that are enabled group members after
waiting the time configured as Shutdown Delay for the initiating UPSs. See
“The shutdown option” on page 36.
2. The initiating UPS waits up to the number of seconds specified as Power
Synchronized Delay to allow time for group members to regain input power. If
all group members already regained input power, this delay is omitted. If all
group members regain input power during the delay, the rest of the delay is
cancelled. To configure Power Synchronized Delay, see “Configure a
Synchronized Control Group member” on page 43.
3. Return Delay starts when the initiating UPS is at its configured Minimum
Battery Capacity (or Return Runtime Duration). See “The shutdown option”
on page 36.
Minimum Battery Capacity (or Return Runtime Duration) of the initiating
UPS is also required of group members. However, you can reduce a group
member’s requirement by configuring that member’s Minimum Battery
Capacity Offset (or Return Runtime Duration Offset), e.g., if the initiator’s
Minimum Battery Capacity is 50%, and a member’s Minimum Battery
Capacity Offset is 5%, that member needs battery capacity of 45% to reboot.
See “Configure a Synchronized Control Group member” on page 43.
ups -c
GraceReboot
(command line
interface)
• This action is similar to Reboot UPS, but with an additional delay before the
shutdown. Attached equipment shuts down only after the UPS (or the initiating
UPS, for a Synchronized Control Group action) waits the Maximum Required
Delay, which is calculated as described in “PowerChute Network Shutdown
configuration parameters” on page 45.
• For a UPS with outlet groups, Power On Delay occurs after the UPS turns on and
before an outlet group turns on. On the UPS tab, you configure Power On Delay
for each outlet group through the settings option under Outlet Groups
. See “The
settings option (including automatic load-shedding)” on page 40.
Action Definition