2.3.3 REPO Connection
The Nfinity is equipped with a Remote Emergency Power Off (REPO) connection.
Figure 2 REPO switch connections
NOTE
A jumper is factory installed between pins 1 & 2 to disable the Control Switch (SW2).
This will prevent the unit from being started during installation. This jumper must
be removed in order to start the unit.
!
CAUTION
To maintain safety, Signal Edge Low Voltage (SELV) barriers, and electromagnetic
compatibility, signal cables should be segregated and run separately from power cables.
NOTE
Remove jumper before wiring.
If the installation does not
require connection to a REPO
system, the jumper must be
removed.
1234
Key to REPO switch connections
1. 24 V DC, 50mA
2. Sense
3. Sense
4. Ground
REPO connections
for normally open
switch system
REPO jumper
connected
as shipped
REPO connections
for normally closed
switch system (fail-safe)
Hanger for cable-tie
to strain relief REPO
wiring
REPO switch
on rear of unit