Emerson 60HZ Power Supply User Manual


 
Battery Installation
22
3.3 External Battery Cabinet Installation
3.3.1 Battery Cabinets
Figure 10 Battery cabinets for Liebert NX
The same model battery cabinet may be installed in parallel in multiple cabinet strings for additional
capacity. Battery run time depends on the cabinet model, the number of cabinets and the load on the
UPS.
Handling—The battery cabinet has casters to facilitate movement over short distances. The bottoms
of the battery cabinets are reinforced to permit movement by forklift over longer distances.
Inspection—Remove all panels and visually inspect the batteries, bus connections and cabinet for
any damage. Exercise caution: voltage is present within the battery cabinet even before installation.
If there are signs of damage, do not proceed. Call Liebert Services at 1-800-542-2378.
Storage—The batteries can be stored for up to six months without appreciable deterioration. If plan-
ning to store a battery cabinet for longer than six months or at temperatures higher than 77°F (25°C),
contact Liebert Services for recommended precautions.
When installing an external battery cabinet that is NOT a Liebert NX battery cabinet, the customer
must provide overcurrent protection. See Table 8 for sizing of protection devices.
!
CAUTION
Any battery system should be installed by properly trained and qualified personnel.
NOTE
When using an external battery supply that is not provided by Liebert, refer to the battery
manufacturer’s installation manual for battery installation and maintenance instructions,
available on the manufacturer’s Web site.
NOTE
When replacing batteries, Liebert recommends that the all batteries in external cabinets be the
same type. See Table 11 for a list of batteries that are approved for use with this product.
Top Cable Entry
Battery Trays
BCB Plate and BCB
Optional Alber BDSi
Data Collection/Load
Module
Optional Alber
BDSi Controller
Module
Liebert 49" Battery Cabinet
Liebert 33" Battery Cabinet