52 Operating Manual TX200 S6
Hardware installation
– You must ensure that the safety mechanisms on the server, e.g. stoppers or
retaining systems, are functioning correctly.
– The shape of the rack support uprights must ensure that the support
systems can be bolted to the front.
The support systems have a linear alignment feature to ensure that they can
be adjusted to different rack depths.
– No cable management support (delivered with the mounting kit).
– Climatic conditions:
An unobstructed air intake in the rack front and air discharge in the rear
cover of the rack are essential for ventilation of the installed server.
In general, the ventilation concept ensures that the necessary cooling is
achieved by the horizontal self-ventilation of the installed devices (air flow
from the front to the rear).
– Power supply:
For installation in 3rd party racks, you must ensure that the appropriate
socket strips are present.
4.3.2 Installation in PRIMECENTER/DataCenter/
19-inch standard rack
For installation in a PRIMECENTER/DataCenter rack, the following parts are
required:
– Support bracket (for the EMEA market)
– One support system on the left and one on the right
– M5 centering fixtures (screws with integrated plugwashers)
I – The descriptions and figures in this section refer to the current
support system. For other support systems you will find the
appropriate description in the packaging of the rack mounting kit.
– General information regarding server installation in the rack is
included in the technical manual for the appropriate rack.