HP (Hewlett-Packard) A7540-96010 Switch User Manual


 
Installing
28 HP StorageWorks 2/8q Fibre Channel Switch Installation Guide
Installing and initially configuring the switch
Installing a 2/8q FC Switch involves the following steps, each of which is discussed in the
following sections:
Unpack the switch and verify carton contents, page 28
Mount the switch, page 29
Install SFP transceivers, page 34
Connect the cables, page 35
Configure the switch, page 36
Unpack the switch and verify carton contents
The 2/8q FC Switch is shipped with the components shown in Figure 5.
Figure 5: Switch carton contents
1 2/8q FC Switch
2 2/8q FC Switch Quick Start Installation Instructions (printed)
3 Power cable (approved for use in the United States)
4 Mounting adapter brackets
5 Screws for the mounting adapter brackets (6)
6 Rubber feet (4)
7 Small Form Factor Pluggable (SFP) transceivers (4)
1
3
2
7
6
4
5