With the z10 BC, signifi cant steps have been taken in the
area of server availability with a focus on reducing pre-
planning requirements. Pre-planning requirements are
minimized by delivering and reserving 8 GB for HSA so the
maximum confi guration capabilities can be exploited. And
with the introduction of the ability to seamlessly include
such events as creation of LPARs, inclusion of logical
subsystems, changing logical processor defi nitions in an
LPAR, and the introduction of cryptography into an LPAR.
Features that carry forward from previous generation pro-
cessors include the ability to dynamically enable I/O, and
the dynamic swapping of processor types.
Hardware System Area (HSA)
Fixed HSA of 8 GB is provided as standard with the z10
BC. The HSA has been designed to eliminate planning for
HSA and makes all the memory purchased by customers
available for customer use. Preplanning for HSA expansion
for confi gurations will be eliminated as HCD/IOCP will, via
the IOCDS process, always reserve:
2 Logical Channel Subsystems (LCSS), pre-defi ned
30 Logical Partitions (LPARs), pre-defi ned
Subchannel set 0 with 63.75k devices
Subchannel set 1 with 64K-1 devices
Dynamic I/O Reconfi guration – always enabled by
default
Concurrent Patch – always enabled by default
Add/Change the number of logical CP, IFL, ICF, zAAP,
zIIP, processors per partition and add SAPs to the con-
fi guration
Dynamic LPAR PU assignment optimization CPs, ICFs,
IFLs, zAAPs, zIIPs, SAPs
Dynamically Add/Remove Crypto (no LPAR deactivation
required)
Redundant I/O Interconnect
In the event of a failure or customer initiated action such
as the replacement of an HCA/STI fanout card, the z10 BC
i
s designed to provide access to your I/O devices through
another HCA/STI to the affected I/O domains. This is exclu-
sive to System z10 and System z9.
Enhanced Driver Maintenance
One of the greatest contributors to downtime during
planned outages is Licensed Internal Code (LIC) updates.
When properly confi gured, z10 BC is designed to permit
select planned LIC updates.
A new query function has been added to validate LIC EDM
requirements in advance. Enhanced programmatic internal
controls have been added to help eliminate manual analy-
sis by the service team of certain exception conditions.
With the z10 BC, PR/SM code has been enhanced to allow
multiple EDM ‘From’ sync points. Automatic apply of EDM
licensed internal change requirements is now limited to
EDM and the licensed internal code changes update pro-
cess.
There are several reliability, availability, and serviceability
(RAS) enhancements that have been made to the HMC/SE
based on the feedback from the System z9 Enhanced
Driver Maintenance fi eld experience.
Change to better handle intermittent customer network
issues
EDM performance improvements
New EDM user interface features to allow for customer
and service personnel to better plan for the EDM
A new option to check all licensed internal code which
can be executed in advance of the EDM preload or
activate.