Liebert XDC Network Card User Manual


 
Product Description
9
1.4.3 Positioning the Liebert XDC with Floor Stand
Install the Liebert XDC according to the site-specific documentation and secure the unit to the floor.
The Liebert XDC can be installed near a wall or another Liebert XDC. There must be at least 3 feet
(914mm) clearance in front of the Liebert XDC for service access. When the Liebert XDC is combined
with the optional water/glycol floor stand, Liebert recommends leaving 3 feet (914mm) of clearance on
the left side of the unit.
A Liebert XDC on a floor stand is 102 inches (2591 mm) high (see Figure 9). The unit can be raised or
lowered 1.5 inches (38.1 mm) with the leveling feet.
Figure 9 Dimensions and clearances for Liebert XDC on floor stand
78"
(1981mm)
102"
(2591mm)
24" Nominal
610 mm
Shaded areas indicate a recommended
cleareance of 36" (914mm) for component
access and water/glycol piping.