MGE UPS Systems GES-152L Power Supply User Manual


 
Always “On” UPS Systems Inc.
19
Battery Bank Installation
Install up to 8 battery banks per L Series UPS following the instructions below.
Caution: Make sure the UPS is shutdown and unplugged before connecting additional
Battery Packs (refer to Switching the UPS “Off” section, page 11)
1. Locate the external battery connector located at the rear of the UPS.
2. Make sure you are connecting the connector correctly or problems will occur.
3. Insert the battery bank connector into the UPS.
4. The UPS is now ready to be turned on with extended runtime.
To install additional battery banks, repeat this procedure using the battery bank connectors on
the back of the battery banks.
Note: Do not stack battery banks, and make sure proper polarity.
1 2
3
4
BLACK
RED