UPS MAINTENANCE
EATON Powerware
®
9125 Two-in-One UPS (5000/6000 VA) User’s Guide S 164201513 Rev B
www.powerware.com
45
5. Slide the new battery trays into the chassis.
6. Reinstall the battery retaining bracket.
7. Replace the lower UPS front cover.
Testing New Batteries
NOTE The batteries must be fully charged and the UPS must not be in Battery mode to
perform the battery test.
NOTE For an accurate battery test, test the UPS with at least 50% load applied to the UPS.
To test the new batteries:
1. Plug the UPS into a power outlet (apply utility power on hardwired
models) for 24 hours to charge the battery.
2. After charging the battery, press and hold the
button for three
seconds to initiate a battery test.
The UPS cycles the bar graph indicators twice, verifies the battery
converter, and schedules the battery test to occur within 24 hours.