RuggedCom RS900G Switch User Manual


 
10
2008 RuggedCom Inc. All rights reserved Rev104
2.3 HIPOT (Dielectric Strength) Testing
Units which are to be “HIPOT” tested in the field must have the braided ground cable disconnected
(see Figure 2.3.1) during the HIPOT test. This is required in order to prevent the transient/surge
suppression circuitry, which is connected to Surge Ground (see Figure 2.3.1), from being activated
during the HIPOT test.
Figure 2.3.1 HIPOT (Dielectric Strength) Testing