96047 First Edition 3-3
Installation Overview
■ Instructions
The following is an overview of the installation procedure to install the UPS in
the L180 and L700 Tape Libraries:
1. Open the front door.
2. Open the rear door.
Note: You can remove the doors for ease of installation.
3. Power-off the library and all the tape drives.
4. Unpack the UPS, redundant switch, mounting hardware, and
documentation.
5. Install the rail kits for the UPS in the rack area.
Note: The rail kits and mounting hardware are included in the packaging for
each component.
Figure 3-1 shows the location of the equipment.
WARNING:
Personal injury. The power supplies are heavy and require more than
one person to lift and install them. Make sure you use proper lifting
techniques when installing the UPS. The L180 UPS weighs 28.6 kg (63 lb)
and the L700 UPS weighs 51.8 kg (114 lb).
6. Install the first (lower) UPS in the rack area. This is UPS B.
7. Install the second (upper) UPS in the rack area. This is UPS A.
Important:
Reconnect the battery cables. The batteries are shipped disconnected
from the UPS. Remove the front cover of the UPS and connect the
batteries to the power supply.
Figure 3-1. UPS Component Locations
C67334
S
ERIAL P
O
RT B
SERIAL PORT A
OUTLET STRI
P
REDUNDANT
SWITCH
UPS A
UPS B