Acer 7745 Laptop User Manual


 
Chapter 3 49
Disassembly Process
The disassembly process is divided into the following sections:
External components disassembly
Main unit disassembly
LCD module disassembly
The flowcharts provided in the succeeding disassembly sections illustrate the entire disassembly sequence.
Observe the order of the sequence to avoid damage to any of the hardware components. For example, if you
want to remove the Mainboard, you must first remove the Keyboard, and LCD Module then disassemble the
inside assembly frame in that order.
Main Screw List
Screw Quantity Acer Part Number
M2.0*3L(BK) 14 86.ARE07.002
M2.5*5L(NI) 8
M2.5*4L(BNI) 12 86.T23V7.009
M3.0*3.5L(NI) 6 86.TDY07.003
M2.5*5L(BNI) 7 TBD
M2.0*5L 4 86.T23V7.010
M2.5*6L(BNI) 38 86.A08V7.004
M2.5*2L(NI) 4 86.EDM07.002