8 40kW InfraStruXure PDU
Connect input conductors
At the Main Input switch, connect the input wiring according to the labels on the switch and the
illustrations below. See the table “Torque specs and tools required” on page 3 for specific information
about connecting to each terminal.
Electrical
Hazar
d
A licensed electrician must connect input conductors to the PDU!
Warning
Connect the conductors to the terminals according to the labels on the
terminals. Use copper conductors only.
400V input with an isolation input
transformer:
L1, L2, L3, PE
PE
L1
L2
L3
400V input without an isolation input
transformer:
L1, L2, L3, N, PE
PE
L1
L2
L3