Cisco Systems 10700 Network Router User Manual


 
5-5
Cisco 12000/10700 v3.1 Router Manager User Guide
OL-3865-01
Chapter 5 Managing Modules
Module Configuration
Step 3 Enter additional descriptions into the Description 1 and Description 2 fields in the Additional
Descriptions area (if required). Entering additional descriptions is optional.
Step 4 Choose Commission to commission the selected module. An Action Report window appears confirming
that the commissioning action was completed successfully.
Figure 5-2 Action Report Window
Step 5
Choose Close to close the Action Report window.
The selected module is now commissioned. Commissioning a GRP or any supporting module initiates
the following activities:
Heartbeat polling begins on the object
The state is changed to normal
Status data becomes available
Commissioning a line card initiates the following activities:
All interfaces on the line card are also commissioned
Heartbeat polling begins on the line card and interfaces
The line card and active interfaces are placed in the normal state
Any interfaces that are pre-deployed but not active change to the errored state
Status data becomes available on the line card and interfaces
Decommissioning a Selected Module
Note You can select multiple Modules from the Module object selector list. Selecting multiple modules allows
you to decommission all of the selected modules simultaneously. You can choose multiple modules in a
list by holding down the Shift key and then selecting the first and last module in the list. You can choose
multiple individual modules by holding down the Ctrl key and clicking on the individual modules.