Appendix E Site Planning and Maintenance Records
Site Preparation Checklist
Ta b l e E-1 Site Planning Checklist
Task No. Planning Activity Verified By Time Date
1 Space evaluation:
Space and layout
Floor covering
Impact and vibration
Lighting
Maintenance access
2 Environmental evaluation:
Ambient temperature
Humidity
Altitude
Atmospheric contamination
airflow
3 Power evaluation:
Input power type
Power receptacles
1
Receptacle proximity to the
equipment
Dedicated circuit for power supply
Dedicated (separate) circuits for
redundant power supplies
UPS
2
for power failures
1. Verify that the power supply installed in the chassis has a dedicated AC source circuit.
2. UPS = uninterruptible power supply.
4 Grounding evaluation:
Circuit breaker size
CO ground (AC- powered systems)
5 Cable and interface equipment
evaluation:
Cable type
Connector type
Cable distance limitations
Interface equipment (transceivers)
6 EMI
3
evaluation:
Distance limitations for signaling
Site wiring
RFI
4