Site-Planning Checklist
Ta b l e 2-2 Site-Planning Checklist
Task No. Planning Activity Verified by Time Date
1 Space evaluation:
Space and layout
Floor covering
Impact and vibration
Lighting
Maintenance access
2 Environmental evaluation:
Ambient temperature
Humidity
Altitude
Atmospheric contamination
Airflow
3 Power evaluation:
Input power type
Receptacle proximity to the equipment
Dedicated (separate) circuits for redundant
power supplies
UPS for power failures
4 Grounding evaluation:
Circuit breaker size
5 Cable and interface equipment evaluation:
Cable type
Connector type
Cable distance limitations
Interface equipment (transceivers)
6 EMI evaluation:
Distance limitations for signaling
Site wiring
RFI levels