Modifications reserved Page 37/57
OPM_LPS_3UO_30K_40K_0US_V010.doc Operating Manual LP 33 Series 30 & 40 kVA
7.1.2 UPS shutdown with load transfer on manual bypass (Q2)
The purpose of this procedure is to supply the load directly by mains through manual bypass Q2.
This procedure is normally performed when the UPS must be completely switched OFF for maintenance
or service purpose, performed by an authorized Service Center.
NOTE !
This procedure must not be performed if the UPS is used as frequency converter.
1. Switch OFF the inverter by entering the screen:
MENU/COMMAND MENU/INVERTER OFF
Attention: to switch OFF permanently the inverter the key
Enter must be pressed 2 times.
COMMAND MENU
INVERTER ON
INVERTER OFF *
The output will be supplied by the mains through the automatic
bypass.
LP 33 40kVA
APPLICAT. ON UTILITY
= 70%
2. Switch ON the maintenance bypass Q2 (Pos. I).
LP 33 40kVA
APPL. ON MANUAL DEV.
= 70%
3. Switch OFF the output switch Q1 (Pos. 0).
4. Perform the command total off.
5. Remove the battery fuses F5, F6, F7 and eventual external fuses in case of external battery.
Continue ►