2
VARIABLE
REGULATOR
GAS CONTROL
VALVE
FLAME CONTROL
SOLENOID
KNOB
SCREW
NUT
VARIABLE
REGULATOR
JAM NUT
VARIABLE
REGULATOR
SOLENOID
WASHER
WASHER
PLUNGER
CAUTION
Risk of damage to control.
Ensure wires are placed into correct color coded terminals
without touching other wires.
• Incorrect placement or crossed wires may damage wall
control.
Figure 1.
Installing the Hi/Lo Solenoid
1. Install the solenoid (see Figure 1).
2. Remove screw and knob from variable regulator and
discard. Unscrew nut from regulator and discard.
3. Remove the bag containing a washer and blue and
red plungers from the side of the fl ame control sole-
noid. Place washer on fl ame control solenoid.
4. Insert correct plunger (blue - natural gas, red - pro-
pane) into the fl ame control solenoid. Thread the
fl ame control solenoid with correct plunger into the
thread hole in the variable regulator. Turn solenoid
into valve approximately two full turns. Do not tighten
or damage may occur.
5. Connect two pin molex connector from the fl ame con-
trol solenoid to the fi rst two pin molex plug on the con-
trol box, as noted on the control module label.
6. Refer to Setting Flame Height/Manifold Pressure in-
structions on page 4.
6. Place front cover plate onto wall control.
7.
Place bottom of wall control faceplate into grooves.
Snap