Connection Combination #2:
Power Module (5kVA) + Transformer Module (5kVA) + Battery Module
Plug the transformer module into the power module.
Plug the transformer module's connector cable
A
directly into either of the
5kVA power module's AC Output 2 Receptacles
B
. NOTE: this cable should
only be plugged into the 5kVA power module.
Plug your equipment into the power module and
transfer module.
Plug your 200/208/220/230/240V AC equipment power cords
C
directly into
the power module's AC Output Receptacles
D
. Plug your 120V AC equipment
power cords
E
directly into the transformer module's AC output receptacles
F
.
Plug the power module into a wall receptacle.
Plug the power module's AC input cord
G
directly into a wall receptacle
H
providing 200/208/220/230 or 240V AC utility power.
Connect the battery module to the power module.
Consult the owner's manual that came with your battery module. Fully insert
the connector on the end of the battery module's cable
I
into the connector
on the rear panel of the power module
J
. Small sparks may occur; this is
normal. NOTE: the power module does not contain internal batteries and will
not start until a battery module is connected. The battery modules are fully
charged prior to shipping. However, before expecting full backup capability
(particularly if the battery module has been stored for an extended period)
after the UPS system is connected to a utility power source, allow the battery
module to recharge for 12 hours. Once the UPS system is in use, it will charge
the batteries and maintain the charge level automatically. NOTE: The 5kVA
Power Module is shipped with a Battery Module which is not expandable;
however, the Power Module is fully compatible with Tripp Lite Battery
Modules which are expandable (Tripp Lite model # BP240V10RT-3U, sold
separately) if extended runtime is required.