3Com 510M-FBP Network Card User Manual


 
3 - 10 ONline Ethernet 10BASE-FB Module Installation and Operation Guide
Installing the Module
You do not need to power down the ONline System Concentrator to install
the 10BASE-FB Modules. You can insert or remove the module while the
concentrator is operating (this is called a hot swap).
To install a 10BASE-FB Module:
1. Do one of the following:
If you do not have a management module installed in the
concentrator, set the dip switches on the board (if different from
the default setting). After you complete the installation
procedure, go to the Monitoring the Front Panel section to verify
the installation.
If you have a management module installed in the concentrator,
complete this installation procedure and then configure the
module using the commands as described in the Configuring the
Module section.
2. Locate a blank slot in the concentrator. If there is no blank slot,
remove a blank panel on the concentrator to expose a slot for a
10BASE-FB Module.
Switch Label Function
Factory
Default
Switch Setting
Off On
9 LOL EN Enable/disable
module Low
Light Detection
enable disable enable
10 Not Used
Table 3-4. Dip Switch S2 Settings (Continued)