Page 23 | AlliedWare™ OS How To Note: EPSR
Example 5: EPSR with management stacking
Example 5: EPSR with management stacking
In this example:
three switches are stacked together, so you can manage all three switches by entering
commands into the CLI of any one of them
the three switches are also configured as an EPSR domain
vlan
1
000 is used as the stacking VLAN and as the EPSR control VLAN. Stacked switches
use the stacking VLAN to communicate with each other
the data VLAN for EPSR is vlan20
ports on the stacked switches are numbered using the stacking scheme of hostid.0.port
Master
Node
(host1)
Transit
Node
(host3)
Transit
Node
(host2)
epsr-example-stack
SP
port 1.0.1:
primary
port 1.0.2:
secondary
vlan45
vlan30
port 2.0.1
port 2.0.2 port 3.0.2