Installing the FLM Power Supply
Ensure the CTFLP module circuit breaker is OFF.
1. Unlock and open the front enclosure door.
To remove the front door from the
enclosure, squeeze the edges of the
enclosure together. This will allow the pins
at the top of the door to slip out of the side
enclosure panels.
2. The top door of the enclosure is hinged on
the back edge.
3. Lower the FLM module into the enclosure
so that the guide pins on the FLM and the
enclosure engage.
4. Push the module until a light “snap” is felt
as the contacts lock into place.
5. Pull lightly on the module. If properly seated
the module will not easily disengage.
6. Turn the utility power ON.
7. Turn the module breaker switch ON.
8. The green Indicator lamp should be ON.
9. Using a voltmeter, verify utility voltage at
the coax connection.