INSTALLATION
EATON Powerware
®
BladeUPS
®
Bar Installation Guide S 164201723 Rev P01
8
4. Install an M6 hex nut onto each of the three wireway studs to
secure the wireway to the rear of the rack. Install the first stud in
the fourth hole location from the bottom. Do not tighten the nuts.
Figure 4 shows the nuts installed.
5. Loosen the three adjustment screws on each side of the wireway
housing and adjust the side brackets for the depth of the rack. Do
not retighten the screws.
6. Install six M6
×12 pan-head screws and M6 split lock washers to
secure the two wireway side brackets to the front of the rack.
Install the first screws in the fifth hole location from the bottom.
Torque the screws to 5.1 ± 0.8 Nm (45 ± 7lbin).
7. Tighten the three M6 hex nuts installed in Step 4. Torque the nuts
to 5.1 ± 0.8 Nm (45 ± 7lbin).
8. Retighten the six side bracket adjustment screws loosened in
Step 5. Torque to 3.4 Nm (30 lb in).
Rear of Rack
Front of Rack
M6HexNutson
Wireway Studs
(3 places)
Side Bracket
Adjustment
Screws
(3 places
each side)
M6×12 Pan-Head
Screws and M6 Split
Lock Washers
(3 places each side)
Adjustable
Side Brackets
(1 each side)
Wireway
Housing
Figure 3. Wireway Installation