Chapter 1 Setting Up the Sun Fire X2100 M2 Server Hardware 7
▼ To Apply Standby Power for Initial Service
Processor Configuration
Use this procedure to apply standby power to the service processor (SP) before initial
configuration.
Caution – Do not operate the server without all fans, component heatsinks, air baffles,
and the cover installed. Severe damage to server components can occur if
operated
without adequate cooling mechanisms.
1. Connect a grounded AC power cord to the AC power connector on the back panel
of the server and to a grounded AC power outlet.
In standby power mode, the Power/OK LED on the front panel flashes, indicating
that the SP is working. See FIGURE 1-3 and TABLE 1-2.
FIGURE 1-3 Front Panel
2. Continue with initial software setup tasks, as described in Chapter 2.
Note – At this point, standby power is supplied only to the service processor and power
supply fans. You can proceed to Chapter 2 of this guide to begin initial configuration. Do
not apply main power to the rest of the server until you are ready to install a platform
operating system.
TABLE 1-2 Front Panel
Label Button/LED/Port Label Button/LED/port
1 System identification button/LED 5 Optional hard disk drive 0
2 Fault LED 6 USB 2.0 connectors (2)
3 Power/OK LED 7 Optional DVD drive
4 Power button 8 Optional hard disk drive 1