6 Battery Rack Assembly and Installation Manual
Installation Site
Installation considerations
The installation site should adhere to the following requirements:
• There should be ample room for performing rack assembly, battery installation, maintenance,
and possible battery replacement.
• Aisle spacing should be in accordance with applicable code requirements.
• Racks should be set on a firm and reasonably level surface. Shimming up to a maximum of
6 mm [0.25 in.] may be used to level corner posts both front-to-back and side-to-side.
• Consider all requirements and restrictions with respect to floor loading.
• Batteries must remain in a climate-controlled environment having a temperature range of 22° to
25° C [72° to 77° F] and a relative humidity of 0% to 95%, non-condensing.
• Batteries should not be exposed to excessive moisture, construction dirt, corrosive elements,
and other contaminants.
Installation equipment
Prior to assembling racks, ensure availability of the following tools and equipment:
Torque specifications
• Open end/box wrenches (SAE dimensions) • Battery lifting device (rated)
• Ratchet set w/sockets (SAE dimension)—3/8” • Step ladder or stepping stool
• Torque wrench • Tape measure
• Standard, Phillips, and torx-head screwdrivers • Chalk line
• Concrete drill (for floor anchoring, if applicable) • T-square
• Voltmeter • Level
• Ohmmeter (for ground testing) • Felt tip marker
• Floor shims (user supplied) • Protective boot (to cover cable lugs)
STANDARD BOLT BATTERY TERMINAL
Bolt Diameter Torque Battery Type Torque
mm inches Nm in-lbs Brand Nm in-lbs
6 1/4 7 60 Power 7.9 70
10 3/8 27 240 Fiamm 11.3 100
12 1/2 68 600