American Power Conversion 400kW1MW Power Supply User Manual


 
6 Battery Rack Assembly and Installation Manual
Installation Site
Installation considerations
The installation site should adhere to the following requirements:
There should be ample room for performing rack assembly, battery installation, maintenance,
and possible battery replacement.
Aisle spacing should be in accordance with applicable code requirements.
Racks should be set on a firm and reasonably level surface. Shimming up to a maximum of
6 mm [0.25 in.] may be used to level corner posts both front-to-back and side-to-side.
Consider all requirements and restrictions with respect to floor loading.
Batteries must remain in a climate-controlled environment having a temperature range of 22° to
25° C [72° to 77° F] and a relative humidity of 0% to 95%, non-condensing.
Batteries should not be exposed to excessive moisture, construction dirt, corrosive elements,
and other contaminants.
Installation equipment
Prior to assembling racks, ensure availability of the following tools and equipment:
Torque specifications
Open end/box wrenches (SAE dimensions) Battery lifting device (rated)
Ratchet set w/sockets (SAE dimension)—3/8” Step ladder or stepping stool
Torque wrench Tape measure
Standard, Phillips, and torx-head screwdrivers Chalk line
Concrete drill (for floor anchoring, if applicable) T-square
Voltmeter Level
Ohmmeter (for ground testing) Felt tip marker
Floor shims (user supplied) Protective boot (to cover cable lugs)
STANDARD BOLT BATTERY TERMINAL
Bolt Diameter Torque Battery Type Torque
mm inches Nm in-lbs Brand Nm in-lbs
6 1/4 7 60 Power 7.9 70
10 3/8 27 240 Fiamm 11.3 100
12 1/2 68 600