American Power Conversion MW Power Supply User Manual


 
Electrical Installation: Bypass Static Switch Wiring
Symmetra MW 1000 kW 480 V Installation - 990-4112E 19
Top cable entry
Loosen the 8 bolts to remove top cover.
Drill holes for conduits. Re-fit the covers. Install the conduits.
Feed cables through conduits. Connect cables at cable connection points as illustrated.
Connect grounding electrode conductor to busbar locations as shown.
Note
No drilling or cutting should take place over the top of the UPS.
2.3 in / 58 mm
1.75 in /
44.45 mm
1.75 in /
44.45 mm
X022
X021
X007
X010
X011
X008B
X008A
X012
X013
X014A
X014B
X017
X405
~~
Normal
UPS Summary
Normal
L1 IN
L2 IN
L3 IN
L1 OUT
L2 OUT
L3 OUT
L1 IN
L1 OUT
L2 IN
L2 OUT
L3 IN
L3 OUT
PE
Top view of top cable entry
Port for communication cables
Top view of AC IN & OUT cable
connections
