Electrical Installation: External Bypass Static Switch Wiring
Symmetra MW 800 kW 3 × 400/230 V Installation - 990-1510D 19
Top cable entry
Loosen the 8 screws to remove top covers. Drill holes for grommets. Re-fit the covers and
install the grommets.
Feed the cables through the grommets. Connect cables at cable connection points.
Connect grounding electrode conductor to busbar locations.
2.3 in / 58 mm
1.75 in /
44.45 mm
1.75 in /
44.45 mm
X022
X021
X007
X010
X011
X008B
X008A
X012
X013
X014A
X014B
X017
X405
~~
Normal
UPS Summary
Normal
L1 IN
L2 IN
L3 IN
L1 OUT
L2 OUT
L3 OUT
L1 IN
L1 OUT
L2 IN
L2 OUT
L3 IN
L3 OUT
Top view of top cable entry
Port for communication cables
Top view of AC IN & OUT cable
connections
External Bypass SSW
Note
No drilling or cutting should take place over the top of the External Bypass SSW.