Black Box V5.1 Network Card User Manual


 
Black Box Networks PICO systems
Pico Manual v5.1
V5.1 19
Fiber optical link between the two heads.
TP Link
Copper side link between the head and the Network equipment.
RX OK
There is enough light to start communicate through the link.
Level 1
25% of the total (acceptable by the receiver) incoming power
Level 2
50% of the total (acceptable by the receiver) incoming power
Level 3
75% of the total (acceptable by the receiver) incoming power
Saturation
Overload (Overloading can cause stop in the communication, and permanently it can
damage the receiver)
7. If the installation distance is shorter
than 50 meters in that case
realignment is required which can be
done with the device on the picture.
7.1 release the screws
7.2 Pull the regulation nut perfectly to
the front and fix it with the screws!
Please note that this operation should
be done extra carefully because it can
move the transmitter out of the alignment. It must be totally on the front!