Cisco Systems SFS 7000D Switch User Manual


 
CHAPTER
2-1
Cisco SFS 7000P and SFS 7000D InfiniBand Server Switches Hardware Installation Guide
OL-10853-01
2
Preparation for Installation
Planning a proper location for the Cisco SFS 7000P and SFS 7000D Server Switches and the proper
layout of your equipment rack is essential for successful system operation. This chapter describes how
to prepare your site for switch installation and contains these sections:
Safety, page 2-1
Site Requirements, page 2-1
Power Requirements, page 2-5
Site Preparation Checklist, page 2-6
Safety
Safety warnings appear throughout this document in procedures that may harm you if performed
incorrectly. A warning symbol precedes each warning statement. The warnings below are general
warnings that are applicable to the entire publication.
Warning
Only trained and qualified personnel should be allowed to install, replace, or service this equipment.
Statement 1030
Warning
This unit is intended for installation in restricted access areas. A restricted access area can be
accessed only through the use of a special tool, lock and key, or other means of security.
Statement 1017
Site Requirements
These sections describe some of the basic site requirements that you should be aware of as you prepare
to install your Cisco SFS 7000P and SFS 7000D Server Switches. Environmental factors can adversely
affect the performance and longevity of your system. Planning a proper location for the switch and layout
of your equipment rack or wiring closet is essential for successful system operation. You should install
the switch in an enclosed, secure area, ensuring that only qualified personnel have access to the switch
and control of the environment. Equipment that is placed too closely together or placed in inadequately
ventilated areas can cause system overtemperature conditions leading to premature component failures.
In addition, poor equipment placement can make chassis panels inaccessable and difficult to maintain.