Compaq R6000 Power Supply User Manual


 
Installation 2-21
Powering up the R6000 UPS
Turning on the Main Circuit Breaker
After a licensed electrician has the Compaq R6000 UPS properly wired to
utility power, and hardware installation is complete, turn on the AC Mains at
the service panel circuit. The Compaq R6000 UPS will automatically initiate a
self-test. If the self-test is completed successfully, the Compaq R6000 UPS
enters Standby mode, designated by the blinking green LED.
Pressing the ON button
To power up the Compaq R6000 UPS, press the ON button (1) (marked “|”)
until the Green LED glows solid. Load segments will go through a staggered
turn-on sequence.
Figure 2-18. The Compaq R6000 UPS “On” button
Shutting Down the System
To shut down the system:
1. Place the UPS on Standby (See Chapter 3, “Operation”).
2. Disconnect the AC mains by opening switch or circuit breaker at the
utility panel.