Chapter 10 Operator Panel Replacement 10-7
13. Insert the OPNL key, and then set the key to the Service position.
14. Switch on all main line switches for the AC section (ACS) in the power supply
system.
15. Confirm that the XSCF STANDBY LED (green) on the OPNL remains lit.
If it is blinking, wait until it remains lit.
16. Use one of the following methods to start (power on) all domains at once.
■ Press and hold down (for less than four seconds) the POWER switch on the operator
panel.
■ From a console that is connected to XSCF, execute the poweron -a command of
XSCF.
The power to all the domains is turned on, and then the power-on self test (POST) is
executed. When ok prompt displayed on the console of relevant domain, POST is
completed.
For details of the power-on operation, see Section 4.4.2, “Powering the Server On” on
page 4-22, and the SPARC Enterprise M3000/M4000/M5000/M8000/M9000 Servers XSCF
User’s Guide.
17. Confirm that the replaced components are normal by using the showhardconf or
showstatus command of XSCF.
Unless "*" is displayed for the replacement OPNL, it is operating normally.
For details of the showhardconf command and showstatus command, see the
SPARC Enterprise M3000/M4000/M5000/M8000/M9000 Servers XSCF User’s Guide, the
SPARC Enterprise M3000/M4000/M5000/M8000/M9000 Servers XSCF Reference
Manual, or the man page.
Note – The showstatus command displays information on degraded components.
18. Restore the original mode switch setting on the operator panel.
Note – When the maintenance work is completed, be sure to confirm the mode switch
setting and return the switch to Locked.
19. Close the door on the server, and lock it.