INSTALLATION REQUIREMENTS
User Manual VanLink System featuring TouchStar™ Technology - Troll Systems Corporation
2-2 Document VLSG-01 - 10/21/08
2.3 INSTALLATION REQUIREMENTS
The Vanlink System components install easily in a standard 19-inch equipment rack.
Physical characteristics of the Vanlink System components are provided in the
applicable assembly drawings. Both standard and custom rack installations must meet
these dimensional requirements in order to properly accommodate the installation of
the controller.
2.3.1 Power Requirements
Power provided at the vehicle must meet either of the following requirements:
• 120VDC for the V750 Remote Site Controller
• 120VDC for the Router
• 120VDC for the V750 Pan and Tilt Controller
2.3.2 Rack Installation
Vanlink System components rack space requirements are as follows:
2.3.2.1 Rack Space Requirements
• V750 – Requires two rack spaces
• Pan/Tilt controller – Requires two rack spaces unless otherwise specified
• EVDO/3G Router – One rack space (not necessarily rack mounted)
2.3.3 Cable Requirements
All applicable cables may be able to be installed (with the ready connectors) after
installing the Vanlink System components into the equipment rack. Connectors and
cables may vary depending upon each customer’s installation requirements.
Cables may be fabricated in the factory. In some cases, customers may choose to
fabricate the cables themselves to custom lengths for the best possible configuration or
fit within their equipment rack. It is recommended to refer to the System Interconnect
Diagram that will accompany your system to determine the cable requirements for your
system.